Heira Spaces
Kalyani House, Baner, Pune
01 · Residence

Kalyani House

Location
Baner, Pune
Area
3,240 sq ft
Completed
March 2026
Lead material
Kota stone, honed

A four-bedroom home for a family of five, planned around one continuous stone floor and a teak spine that carries every door.

01 — Brief
What the building asked for, and what was decided.
01

The floor runs unbroken from the entrance to the rear verandah: Kota stone, honed, 20mm, laid 600×600 with a 3mm brass inlay at the thresholds.

02

Joinery is Burma teak, 19mm, oiled rather than lacquered, so it can be re-oiled instead of replaced.

03

The opening between kitchen and dining was load-bearing. It was widened to 1200 and carried on a 150 steel lintel.

Kadappa counter, 30mm, pencil edge. Brass tap left to patinate.
Kadappa counter, 30mm, pencil edge. Brass tap left to patinate.
02 — Specification
Named, sized and sourced before work began.
FlooringKota stone, honed, 20mm, 600×600, 3mm brass inlay
WallsLime plaster, three coats, burnished, no paint
JoineryBurma teak, 19mm, oiled, 4mm shadow gap at all reveals
CountersKadappa stone, honed, 30mm, pencil edge
IronmongeryUnlacquered brass, left to patinate
WindowsTeak frames, 6mm clear, brass mesh insect screens
03 — Plates
Same lens, same height, same time of day.
Teak-framed window with brass mesh. Linen loose covers.
Teak-framed window with brass mesh. Linen loose covers.
Lime plaster meeting Kota stone, 3mm brass at the threshold.
Lime plaster meeting Kota stone, 3mm brass at the threshold.
04 — Sequence
One programme, one site lead, trades booked in order.
    Week 01

    Strip out

    Existing tiling and ceilings removed, structure surveyed.

    Week 03

    Structure

    Kitchen opening widened to 1200, steel lintel set and grouted.

    Week 05

    Services

    Plumbing and conduit run, first fix signed off before plaster.

    Week 08

    Stone

    Floor laid from the entrance outward, brass inlay cut on site.

    Week 11

    Joinery

    Teak carcasses fitted, fronts hung and adjusted.

    Week 14

    Handover

    Defects list closed, upkeep book issued.

14
Weeks on site
42
Lines specified
9
Trades sequenced
Next on the schedule · 02

Advait Apartment

Prabhadevi, Mumbai · November 2025
Open →
Advait Apartment, Prabhadevi, Mumbai
Your project

Bring usthe shell.

Send the address, the approximate area and the month you would like to start. We reply within a week with a written note on what is possible.

Hands oiling a teak cabinet in the joinery workshop